Prince2认证题库连载(十七)481. Which is apurpose of the Organization theme? C A. Establishtolerances around the resources utilized on the project B. Provide projectmanagement training to those working within the project C. Establish astrategy for communication between all interested parties of the project D. Implement thecontrols required to permit management by exception 482. Which of thefollowing takes place before the initiation of a project? A 1. Provide theExecutive with a role description 2. Consider thesuccess and failures of similar activities carried out in the past 3. Record andupdate all initial risks in the Daily Log 4. Develop thedetailed Business Case stating why the project is worth doing A. 1,2,3 B. 1,2,4 C. 1,3,4 D. 2,3,4 483. Which is thefirst plan to be created? B A. Project Plan B. Stage Plan C. Team Plan D. Exception Plan 484. Which processinterfaces with corporate or programme management to provide and receiveinformation? B A. Managing ProductDelivery B. Directing aProject C. Controlling aStage D. Managing a StageBoundary 485. What is NOTensured by the Managing Product Delivery process? C A. Suppliersunderstand what is expected of them B. Products ofappropriate quality are delivered C. The ProjectBoard is kept informed of progress on the products D. Work for theteam is agreed with the Project Manager 486. Which is anobjective of the quality review technique? A A. To involve keyinterested parties in checking the product’s quality and in promoting wideracceptance of the product DevOps B. Develop andimprove the specification of a product through continuous assessment C. Correct anytypographical errors found in a product and obtain sign-off during the qualityreview meeting D. Update the statusinformation in the Configuration Item Record when a product is signed-off |