26.Which of these statements is FALSE?
A. The Project Plan is an overview of the total project.
B. For each stage identified in the Project Plan, a Stage Plan is required.+ o. O3 u4 t5 M# F L0 B8 S9 S: \
C. An Exception Plan needs the approval of the next higher level of authority.
D. A Team Plan needs approval by the Project Board.ITSS