571. Which of thefollowing roles can the Project Manager also perform? C                 

1. Change Authority

2. ProjectAssurance

3. Project Support

4. Team Manager

A. 1,2,3

B. 1,2,4

C. 1,3,4

D. 2,3,4

572. Identify themissing word in the following sentence.

A risk consists ofa combination of the (?) of a perceived threat or opportunity occurring and themagnitude of its impact on objective. B

A. outcome

B. probability

C. dis-benefit

D. proximity

573. When would theTeam Manager be required to produce a Checkpoint Report? B

A. When a WorkPackage is being negotiated

B. During thecreation of products by a team

C. On completion ofthe quality checking activities for a product

D. When reviewinghow a stage is progressing

574. How does thePlans theme support the ‘manage by exception ‘principle? B

A. Allows theproject to be broken into manageable stages

B. Offers threelevels of plan for which tolerance can be set

C. Provides anoverview Project Plan and a detailed Stage Plan

D. Reviews anychange to the Business Case at the end stage assessments

575. Identify themissing words in the following sentence.

When creating the(?), the Configuration Item Records will be reviewed to see which products havebeen started, which are currently in review and which have been approved. A

A. Product StatesAccount

B. Stage Plan

C. Benefits ReviewPlan

D. Lesson Log

576. How does theChange theme support the ‘manage by exception’ principle? A

A. Any change to abaselined product that reveals a threat to tolerances must be escalated to theProject Board

B. Any change to aConfiguration Item Record must be escalated to the Project Board

C. Any creation ofa product variant will trigger an Exception Report

D. An ExceptionPlan must be accompanies by a Product States Account

577. Whichstatement describes risk cause? B

A. The impact of arisk on the stage and project tolerance

B. The event thatgave rise to a risk

C. The overallexposure of a risk on the Business Case

D. How likely arisk is to occur in a given project situation

578. Which PRINCE 2principle supports planning only to a level of detail that is manageable andforeseeable? D

A. Continuedbusiness justification

B. Manage byexception

C. Focus onproducts

D. Manage by stages

579. Whichinformation appears in the Business Case? D

A. Details of costand time tolerance agreed for the project

B. Information onthe interested parties and key stakeholders

C. Procurementprocesses for obtaining the selected business solution

D. How the projectis to be funded

581. How does the authorizationof initiation support the defined roles and responsibilities principle? C

A. Requests any necessarylogistical support

B. Designing andappoints the project management team

C. Confirms thatall members of the project team have agreed their roles

D. Approves theProject Product Description

582. What is aresponsibility of the business representative on the Project Board? B

A. Settingtolerance levels for the project

B. Ensuring theproject represents value for money

C. Confirming theproject delivers the required functionality

D. Checking therequired quality levels are achieved by the project’s products

583. Whichstatement correctly describes the relationship between Project Assurance andquality assurance? A

A. Qualityassurance provides assurance to the corporate/programmeorganisation whereasProject Assurance provides assurance to the project’s stakeholders

B. They are boththe responsibility of the Project Board, bur Project Assurance may be delegated

C. They are bothindependent of the project

D. ProjectAssurance ensures that adequate quality assurance is in place for the project

584. How is theProject Product Description used in the initiating a Project process? A

A. Refined whencreating the Project Plan

B. To provide inputto the Communication Management Strategy

C. Aids developmentof procedures for managing issues

D. Updated with anyplanning and control tools to be used by the project

585. What is apurpose of the Change theme? B

A. Prevent changeto anything agreed in the Project Initiation Document

B. Ensure anypotential changes to baseline products are controlled

C. Ensure that the correctversions are delivered to the customer

D. Assess changesto only the specialist products

586. Which documentwould confirm the version numbers of a project’s product? B

A. ConfigurationManagement Records

B. Product StatuesAccount

C. Stage Plan

D. Work Package

587. Which is abenefit of using PRINCE 2? B

A. Stakeholders arekept out of planning and decision-making

B. Participantsunderstand each other’s role and needs

C. Stakeholders arenot involved in assuring the project work

D. All problems areescalated to all stakeholders

588. In whichproduct would a product’s quality tolerance be defined? B

A. Project ProductDescription

B. ProductDescription

C. Stage Plan

D. QualityManagement Strategy

589. Which roleshould produce a Product Status Accounting during the preparation of a plannedproject closure? A

A. Project Support

B. ProjectAssurance

C. Team Manager

D. Qualityassurance

590. What is thepurpose of the risk budget? C

A. To fund risk managementactivities defined in the risk management procedure

B. To fund the costof analyzing requests for change while executing a Work Package

C. Funds includedwithin the project budget to cover the costs of implementing risk response

D. Funds includedwithin the project budget to cover the costs of identifying risks to theproject

591. Whichstatement should appear in a Business Case? C

A. Due tooperational requirements an off-the-shelf solution is the preferred

B. Capacity: Mustproduct 50 more than existing production equipment

C. The ‘do nothing’option is not acceptable here as the business need is critical to ongoingoperations

D. Acceptance

592. Identify themissing words in the following sentence.

PRINCE 2 managementstages relate to (?), which is a factor that differentiates them from technicalstages. D

A. Use of aparticular set of technical skills

B. Use of aspecific set of Team Managers

C. An authorizationfrom corporate or programme management

D. Commitment ofresources

593. In whichactivity would the Project Board normally review a Highlight Report? D

A. Authorizinginitiation

B. Authorizing aStage or Exception Plan

C. Authorizing theproject

D. Giving ad hocdirection

594. Identify themissing word(s) in the following sentence.

Quality planningprovide the definition of the required products with their (?) as a foundationfor Project Board agreement. C

A. customer’squality expectations

B. quality testresults

C. quality criteria

D. owners

595. Where would aTeam Manager find details of how to deal with a new risk? D

A. ConfigurationManagement Strategy

B. Exception Plan

C. QualityManagement Strategy

D. Work Package

596. Which is NOTan event-driven control? A

A. Highlight Report

B. Exception Report

C. ProjectInitiation Documentation

D. End of a stage

597. Whenauthorizing a stage, in which product would be Project Board look for anexplanation of any deviations from the approved plans that are withintolerance? B

A. Lessons Report

B. End Stage Report

C. Benefits ReviewPlan

D. ProjectInitiation Documentation

598. Which of thefollowing information does a Product Description provide? A

1. Necessaryabilities of the people needed to produce the product

2. Why the productis needed and what it will look like

3. Necessaryabilities of the people needed to review the product

4. Time and costneeded to produce the product

A. 1, 2, 3

B. 1, 2, 4

C. 1, 3, 4

D. 2, 3, 4

599. What is apurpose of the Communication Management Strategy? C

A. Ensuring theproject team can use the required reporting tools

B. Producingreports for the Project Board

C. Defining thecommunication method between the Project Board and corporate or programmemanagement

D. Ensuringstakeholders are aware of their responsibilities

600. Which of thefollowing are uses of the Risk Register during the Controlling a Stage process.C

1. Obtain detailson risks to include in a Highlight Report

2. Obtain detailsof risks that may affect the Stage Plan for the next stageITSS

3. Captureuncertainties identified when authorizing a Work Package

4. Obtain detailsof any potential impacts that may affect the Business Case while reviewing thestage status

A. 1,2,3

B. 1,2,4

C. 1,3,4

D. 2,3,4

601. In which planshould project closure activities be planned? B

A. Plan for thesecond stage following project authorization

B. Stage Plan forthe final management stage

C. Initiation StagePlan

D. Team Plan

ITIL培训题库存