211. Target reviewand approval dates for products are defined in which product? D
A. QualityManagement Strategy
B. ProductDescription
C. Project Plan
D. Quality Register
212. When is theQuality Management Strategy prepared? B
A. In Starting Up aProject
B. DuringInitiation
C. As part ofManaging a Stage Boundary
D. As part of theproject mandate
213. When is theIssue Register created? D
A. Managing ProductDelivery
B. Starting up aProject
C. Managing a StageBoundary
D. Initiating aProject
214. If there is arequest to change an APPROVED product, which management product will identifywho is permitted to authorize the change? D
A. Issue Register
B. QualityManagement Strategy
C. ProductDescription
D. ConfigurationManagement Strategy
215. If anoff-specification is acceptance as a concession what else will need to berevised? C
A. Stage Plan
B. Quality review
C. ProductDescription
D. Productbreakdown structure
216. Which of thefollowing is NOT a type of issues addressed within the Change theme? C
A. Request forchange
B. Off-specification
C. Identificationof a new risk
D. Problem/concern
217. In PRINCE 2all potential changes to baselines are dealt with as…? D
A. HighlightReports
B.Off-specifications
C. Configurationitems
D. Project issues
218. Which of thefollowing is a Project Manager control? D
A. Highlight Report
B. Exception Report
C. Project closure
D. Work Packageauthorisation
219. ISO 9001states that all design changes and notifications shall be identified,documented, reviewed and approved by authorized personnel before theirimplementation.
Which of theseoptions allows PRINCE 2 to meet this requirement? A
A. Change control
B. Risk and QualityRegisters
C. End Stageassessments
D. Checkpoint andHighlight Reports
220. Can a ProductDescription be changed, once it has been approved? C
A. Yes, norestriction
B. Never
C. Only via changecontrol
D. Only via a QualityReview action item
221. The ProjectBoard may decide to delegate consideration of requests for change to whatgroup? A
A. A ChangeAuthority
B. ProjectAssurance
C. Project Support
D. Programmemanagement
222. In whichprocess does the Project Manager as the Project Board where the authority formaking change lies? B
A. During Starting Upa Project
B. DuringInitiating a Project
C. In Giving Ad HocDirection
D. When Authorisinga Stage
223. Because thefinal product will exist after the project has finished, what aspect of PRINCE2 is often carried out on an organisation-wide basis? B
A. Planning
B. Configurationmanagement
C. Risk Management
D. End StageAssessments
224. Because the finaldeliverable will exist after the project is finished. PRINCE 2 suggests thatProject Support function handle some work. What is this work called? C
A. Change control
B. The Managementof Risk
C. Configurationmanagement
D. Managing ProductDelivery
225. Which is themissing PRINCE 2 theme?
Business Case,Organisation, Plans, Quality, Risk, Change AND…A
A. Progress
B. Product-basedPlanning
C. ConfigurationManagement
D. Quality Review
226. Where wouldyou start if a question arises on why a particular product was changed? C
A. Issue Log
B. Quality Log
C. ConfigurationItem Records
D. Project Issue
227. Which elementof PRINCE 2 tells the Project Manager where products are at any time, whattheir status is and who is working on them? C
A. Work Package
B. ProductDescription
C. Configurationmanagement Stage Plan
D.
228. The personoperating the configuration management method is called…? A
A. Configurationlibrarian
B. Configurationauditor
C. ProductAssurance
D. Versioncontroller
229. In terms ofconfiguration management what are described as a configuration item? C
A. The resources
B. The plans
C. The products
D. The businessbenefits
230. What name isgiven to the series of reviews and audits that is part of configurationmanagement to ensure conformity between all products and the authorized stateof products as registered in the configuration item records? B
A. Statusaccounting
B. Verification andaudit
C. Quality reviews
D. Qualityassurance
231. Which productsshould have their own Configuration Item Record? D
A. The single endproduct
B. The interimproducts
C. Only ProductDescriptions
D. Every configureditem
232. Which is apurpose of configuration management? A
A. Theadministrative activities concerned with the creation of products
B. The creation ofmanagement products
C. The approval ofspecialist products
D. The definitionof which products will be required
233. A baseline isused in: C
A. Project filing
B. The projectmandate
C. Configurationmanagement
D. Quality review
234. Examining theimpact of an issue is part of? D
A. Quality in aproject environment
B. Configurationcontrol
C. Starting up a Project
D. Change control
235. If there is aneed to know what the content of an old version of a product was, which productwould most help us? B
A. The IssueRegister
B. ConfigurationItem Record
C. Work Packages
D. HighlightReports
236. Which of the followingcorrectly describes the term: Item identifier’ in a configuration item record? B
A. A replicatednumber from another product
B. A uniquereference
C. Any numberingsystem
D. A lable
237. Which is oneof the six aspects of a project that requires management? C
A. Performance
B. Reliability
C. Scope
D. Ease of use
238. How does theControlling a Stage process support the learn from experience principle? B
A. Supports theProject Manager in ensuring products are delivered within the tolerances agreedwith the Project Board
B. Encourages theProject Manager to review the progress of the stage and log any lessons ITIL
C. Requires escalationof issues and risks to the Project Board which threatens the stage or projecttolerances
D. Recommends aWork Package is created to deliver products that require specific skills
239. Which processcovers the authority to initiate a project? C
A. Starting up aProject
B. Initiating aProject
C. Directing aProject
D. Managing a StageBoundary